Department in R9bn shortfall

Bhisho wants clarity on human settlements’ variation orders

A dwindling budget, together with a raised set of standards, has created a shortfall of R9bn for the provincial department of human settlements.
This was revealed during a Bhisho standing committee on public accounts sitting, where the human settlements department was called to account on so-called “variation orders”, which allowed for money to be spent which was not in the budget. Committee chair and UDM MPL Max Mhlati said they wanted to know why there were variation orders.
“We realised that there is money added to projects – huge amounts of money – and we want you to tell us why,” he said. “Treasury must monitor this because it is the function of treasury to monitor funds.
“They must monitor because the variations change the amounts of tenders that had been given out already.
“This 20% variation can open the ground for corruption and we don’t want that.”
Human settlements acting head of department Daluhlanga Mpendu said the variations were as a result of the new norms and standards set by the national department of human settlements.
“New norms and standards came into place which included other features like ceilings, aprons and other things.
“That had a cost effect and we had to align our projects to fit in with those new norms and standards.”
The new norms and standards, Mpendu explained, had increased the cost of projects “by a couple of million”, depending on the stage the project was in. The department had over-committed its budget and one of the reasons was the new norms and standards which, he explained, had meant that a new feature had been added to houses. He said it sometimes happened in mid-project, leading to increased prices.
The national department had set variations at 20%, meaning contractors could go above the tendered amount by 20% when new norms and standards had been issued.
“Remember we did not plan for the new norms and standards, they came midway.
“That impacted on the over-commitment but we are beginning to address that situation and we are comfortable that we are addressing that.”
He said his department wanted to clear the shortfall.
“We have since reduced it by R2bn to R9bn in the last financial year. Reducing the budget over the years has led to those projects not being contained within our medium-term expenditure framework (MTEF) budget. We are going beyond our MTEF budget.”
The department’s variations are:..

This article is free to read if you register or sign in.

If you have already registered or subscribed, please sign in to continue.



Questions or problems? Email helpdesk@dispatchlive.co.za or call 0860 52 52 00.

Would you like to comment on this article?
Register (it's quick and free) or sign in now.

Speech Bubbles

Please read our Comment Policy before commenting.